Plan Your SAP S/4HANA Finance Migration with These Tips

by Ajay Maheshwari, Associate Director, SAP Practice, itelligence, India

September 16, 2016

Ajay Maheshwari explains how you can fix the probable issues that arise during a migration to SAP S4/HANA Finance well in advance and even before the actual migration is kicked off. Why impede the migration process when you can make it a smooth ride? He also explains what to expect out of the SAP General Ledger post migration.

System downtime is one of the key aspects of the migration process. The tips provided in this article aim at reducing the system downtime in the perspective of migration activities, enabling you to deliver a smoother finance migration as well as to cut down the resources required during the migration process. In my experience, the issues that arose during the migration took almost four days to be fixed. With these tips, you can reduce the time spent on your migration.

What Is S/4HANA Finance?

To begin with, I briefly touch upon the terms Simple Finance or S/4HANA Finance to bust any myths around them.

Simple Finance is an exchange innovation in the sense that installation of Simple Finance Add-On replaces the classic SAP Financial Accounting and Controlling (FI-CO) modules with re-engineered SAP Accounting Powered by HANA, leaving all other modules as is. On the other hand, SAP S/4HANA 1511 is a whole gamut of re-engineered SAP ERP applications (not just FI/CO, but pretty much the SAP logistics modules as well). It is also noteworthy to mention that Simple Finance was the first step toward SAP S/4HANA.

The eligibility criteria for installing the Simple Finance Add-On are SAP Business Suite on SAP HANA, SAP ERP Central Component (ECC 6.0), and enhancement package 7. Eligibility criteria for installing SAP S/4HANA are SAP Business Suite on SAP HANA plus ECC 6.0 (enhancement package 7 is not mandatory). Both Simple Finance and S/4HANA require a company running an SAP system to undergo a migration process to achieve the innovations.

At the time of writing this article, the version of SAP S/4HANA 1511 is Feature Pack Stack (FPS) 02 (the earlier version was FPS 01).

Evaluation Before Migration

The new products S/4HANA Finance and SAP S/4HANA 1511 are not compatible with a few components, and some of the SAP services are not currently available. In some cases, you may have to adhere to certain technical requirements before being eligible for migration.

Hence, it is a good investment of time to make technical evaluations before deciding to migrate. These will also help you to plan the resources, timelines, and the overall project.

The following points are handy while taking the decision:

  • Classic SAP Real Estate (SAP RE) is not compatible and not on the roadmap as well. Customers with classic SAP RE must first migrate to SAP Flexible Real Estate (RE-FX) before they can install S/4HANA Finance or migrate to SAP S/4HANA.
  • Companies migrating from the classic General Ledger to S/4HANA Finance or S/4HANA cannot subsequently activate document splitting and parallel ledgers (the SAP General Ledger migration service is currently not compatible with the new product).
  • Companies intending to have balance sheets at the profit center level must first upgrade to the SAP General Ledger and then install S/4HANA Finance or migrate to SAP S/4HANA.
  • Both S/4HANA Finance and SAP S/4HANA 1511 require you to have an additional depreciation area in Asset Accounting (FI-AA) for each additional currency in the SAP General Ledger before the migration process can begin.
  • Companies not having their existing FI-AA aligned to this principle must get it aligned in a separate small project.
  • Both S/4HANA Finance and SAP S/4HANA 1511 require you to activate the Financials Extension (EA-FIN). If not currently active, this must be activated in a separate small project.
  • As of SAP S/4HANA 1511 (not applicable to S/4HANA Finance), you must use the business partner concept to manage your customer and vendor master data. Companies not currently using business partners must synchronize their customers or vendors with business partners before the migration process can begin.

For detailed information about constraints, limitations, and other technical requirements, refer to the relevant Release Information Notes and Conversion Guides applicable to your release of S/4HANA Finance or SAP S/4HANA 1511.

Become Enabled to Deliver a Smooth Migration Process

Once the decision is made to migrate after considering all the technical requirements, companies need to undergo a migration process. The migration process to S/4HANA Finance or SAP S/4HANA 1511 is rather straightforward and can be carried out by functional experts, unlike the SAP General Ledger migration process that requires you to order SAP’s migration service.

With its Conversion Guides and Migration Guides, SAP lays down the technical steps to be followed and the sequence in which the steps must be executed. The latest version of the conversion guide to SAP S/4HANA 1511 can be found here.

At the top of the web page that opens, click the Product Documentation link to locate the conversion guide.

In addition to the steps outlined in the Conversion Guides, a series of steps (if followed) enable you to iron out the data inconsistencies in advance so that the migration process is smooth and does not prolong the system downtime. (The steps, the phases, and a description of the activities completed during each step are listed in Table 1.)

Serial no.

Phase

Activity

1

Before
upgrade

Identify and fix
GL inconsistencies
related to open item
management

2

Before
upgrade

Add parallel
depreciation areas
for parallel currencies
in FI, if not already
done

3

Before
upgrade

Implement the programs
listed in SAP Note 366848

4

Before
upgrade

Identify and fix
FI-AA data inconsistencies
using programs ZACORR130,
ZACORR110_B, and ZACORR55

5

Before
upgrade

Execute transaction
code ASKBN

6

Before
upgrade

Delete held documents

7

Before
upgrade

Reconcile FI-AA (execute
transaction code ABST
or ABST2)

8

Before
upgrade

Run transaction code
AJAB (to close previous
asset fiscal year)

9

Before
upgrade

Reconcile FI-GL with
AP/AR Sub-Ledgers
(report SAPF190 or
report TFC_COMPARE_VZ)

10

Before
upgrade

Reconcile MM-FI (report
RM07MBST or report
RM07MMFI)

11

Before
upgrade

Run program RFINDEX_NACC
(to find and fix inconsistencies
in the index tables)

12

Before
upgrade

Implement SAP Note 1939592
and all the subsequent notes listed
in 1939592
(pre-migration check program)

13

Before
upgrade

Compare ledgers using transaction
code GCAC to ensure that they reconcile

IMG > Migration from SAP ERP to SAP Accounting powered
by SAP HANA > Preparations and Migration of Customizing, Migration)

 

14

Post-
upgrade
activities

New FI-AA configuration
(such as migrating chart of
depreciation, adjusting depreciation
area posting indicators, and maintaining
technical clearing accounts)

15

Post-
upgrade
activities

Adjust Profitability Analysis (CO-PA)
customizing
(delete settings for profitability
segment chars, activation of ABCOPA)

16

Post-
upgrade
activities

Adjust G/L customizing
(Assign ledger to CO version,
assign document type to CO
business transactions, migrate G/L
customizing, define source ledger for
migration of balances)

17

Post-
upgrade
activities

G/L account - Cost element
consistency check

18

Post-
upgrade
activities

Migrate secondary cost
elements to chart of accounts

19

Post-
upgrade
activities

Migrate default account assignments
(from the cost element master to
Change Automatic Account Assignment
[transaction code OKB9])

20

Post-
upgrade
activities

Analysis of transactional data

21

Post-
upgrade
activities

Reconciliation of transactional data

22

Post upgrade activities

Enrich transactional data

23

Post-
upgrade
activities

Check enrichment of transactional data

24

Post-
upgrade
activities

Data migration into
unified journal: line items

25

Post-
upgrade
activities

Check migration
of journal entry

26

Post-
upgrade
activities

Data migration into
unified journal: aggregate deltas

27

Post-
upgrade
activities

Check migration
of balances

28

Post-
upgrade
activities

Initial
depreciation calculation

29

Post-
upgrade
activities

Check initial
depreciation calculation

30

Post-
upgrade
activities

Migrate house banks

31

Post-
upgrade
activities

Activation and migration
of the Material Ledger

32

Post-
upgrade
activities

Migrate Credit Management
(FI-AR-CR) to FSCM-CR

33

Post-
upgrade
activities

Set migration to completed

 

 

 

IMG> Migration from SAP ERP to SAP Accounting
Powered by SAP HANA > Activities after Migration

34

Post-
migration activities

Transfer
application indices

35

Post-
migration activities

Fill due dates
 in FI documents

36

Post-
migration activities

Fill offsetting accounts
in FI documents


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Table 1
Chart of migration steps

G/L Account Data Inconsistencies

The Managing Open Item (XOPVW) flag for Open Item Managed G/L accounts is a key aspect of the S/4HANA Finance or SAP S/4HANA 1511 migration.

For a G/L account that is open-item managed, ensure that all the historical line items have the XOPVW flag active in the BSEG table and the index tables (BSIS and BSAS). If not, the migration programs consider this a data inconsistency.

Why Can the Inconsistency Occur?

With enhancement package 3, you can use transaction code FAGL_ACTIVATE_OP to subsequently activate the Open Item Management indicator in a G/L account. This program ensures the XOPVW flag is activated for all historical line items. In the releases prior to enhancement package 3, program RFSEPA02 was used. However, it was also possible to manually activate the Open Item Management in G/L Master (FS00), even without using the program RFSEPA02, provided the balance in the G/L is zero. If manually activated, all historic line items would not have the flag XOPVW turned on, whereas prospective line items would have the flag turned on.

Which SAP Installations Can Run Into This Issue?

Companies that are not on the SAP General Ledger (i.e.,during the migration from the classic G/L to the S/4HANA Finance Add-On or S/4HANA 1511).

How to Fix This Data Inconsistency

Two options are available to fix this data inconsistency: option A and option B.

Option A: During the migration to SAP S/4HANA 1511 FPS 01, the system is technically upgraded to S4CORE (i.e., the new application layer). Once on S4CORE, you can execute transaction code FAGL_ACTIVATE_OP. However, if SAP Note 2245930 is implemented in your system, it would not be possible to execute transaction code FAGL_ACTIVATE_OP. However, you can de-implement SAP Note 2245930 in an FPS 01 system and then be able to execute transaction code FAGL_ACTIVATE_OP.

In an FPS 02 system, however, there is no way to de-implement SAP Note 2245930. SAP offers a new program for the purpose, which is currently released on a pilot basis. You need to contact SAP Support in order to use the new program.

Here are the steps to be followed in this option:

  1. Clear all the open items in the G/L account, using the Post with Clearing option, by posting the line items to an offsetting account. The balance after you complete this step would be zero.
  1. Remove the Open Item Management flag in the G/L Master (execute transaction code FS00).
  2. Execute transaction code FAGL_ACTIVATE_OP or the new pilot program to switch on the XOPVW flag for all the line items. This would also switch on the Open Item Management indicator in the G/L master.  

With the above steps, the inconsistency would be fixed well in advance rather than being reported during the migration process.

After the migration is done, you need to reset the cleared items that were cleared in step 1 above using transaction code FBRA.

Option B: If the above options are not available and you do not wish to be a pilot customer for the new program, then you need to activate the XOPVW flag at the table level (i.e., tables BSEG, BSIS, and BSAS) using a custom program or using an SAP consulting service.

FI-AA Data Inconsistencies

Hidden data inconsistencies in FI-AA also can prolong the migration process and thereby the system downtime. To avoid data inconsistencies in fixed assets historical data (line items and summary records), it is wise to execute a series of programs well in advance before starting the actual migration. These programs are not part of a standard SAP delivery, but need to be imported in the SAP system through SAP Note 366848.

These programs fix the inconsistency between the line items and summary and also any differences between the closing balances at the end of fiscal year and opening balances at the beginning of a fiscal year. Basically, values in the table ANEP and ANLC are reconstructed.

In addition to reducing the system downtime, there is also a technical reason for why these programs must be executed at this stage. I describe this scenario now.

After the S/4HANA Finance Add-On is installed or the existing system is migrated to S4CORE, many tables are dropped and ANEP and ANLC are two of them. Because the correction programs work on tables ANEP and ANLC, you must repair the values in tables ANEP and ANLC before they are dropped.

I explain what programs must be executed and how to execute them.

Three programs must be executed for all the fiscal years since go-live, as there is no other means to know if a data inconsistency exists: ZACORR130 (copy of RACORR130), ZACORR110_B (copy of RACORR110), and ZACORR55 (copy of RACORR55).

Program ZACORR130 (Copy of RACORR130)

Use transaction code SE38 to access the program ZACORR130. You would see the initial screen as Figure 1.


Figure 1
The initial screen of program ZACORR130

Parameters such as Company Code and Fiscal Year are mandatory. You can use the parameters SO_BUDAT (posting dates) to shorten the time frame.

Assuming a customer went live in the year 2007, the program must be executed since 2007, first in the TEST mode. If the output does not show any records to be corrected, you are lucky. In case it throws any records to be corrected (for example in the FY 2009), execute the program for the same fiscal year without the TEST mode and also make a note of the asset numbers. This program repairs the line items in table ANEP by assigning the appropriate fiscal year. Likewise, execute the programs for all the fiscal years until the last closed fiscal year.

Program ZACORR110_B (Copy of RACORR110)

Execution of ZACORR130 must be followed by ZACORR110_B, for each fiscal year. This program recalculates the values in table ANLC from the line items in table ANEP.

Use transaction code SE38 to access the program ZACORR110_B. You would see the initial screen as shown in Figure 2.


Figure 2
The initial screen of program ZACORR110_B

As can be seen in Figure 2, the CCODE (company code), ASSETNO (asset number), and FISCYEAR (fiscal year) fields are mandatory. Enter the asset numbers that you earlier made a note of or enter all the asset numbers (from 1 to 9999999) to repair any inconsistencies other than the one identified by program ZACORR130.

Here is a sample of what the program ZACORR110_B does.

Before you execute program ZACORR110_B, the summary values in ANLC are 675998.21.

Use transaction code SE16 or SE16N to access the Table ANLC for the asset (310064) and Fiscal Year (2005). You then see the screen shown in Figure 3, which shows the value in table ANLC as 675998.21.


Figure 3
Asset 310064 in table ANLC before executing program ZACORR110_B

Use transaction code SE16 or SE16N to access table ANEP for the asset (310064) and fiscal year (2005). As shown in Figure 4, note that the total of line items in table ANEP is 113,554.33.


Figure 4
Line items for asset 310064 in table ANEP for fiscal year 2005

Report ZACORR110_B highlights the same totals.

Execute transaction code SE38 to execute the program ZACORR110_B. This action displays the screen shown in Figure 5.


Figure 5
Output of program ZACORR110_B

As you can see, it shows the summary values in table ANLC (675998.21) and sum total of line items in table ANEP as 113554.33.

Program ZACORR55 (Copy of RACORR55)

The values recalculated by program ZACORR110_B must now be updated using program ZACORR55.

Use transaction code SE38 to access the program ZACORR55. You would see the initial screen as Figure 6.


Figure 6
The initial screen of program ZACORR55

Execute this report for the affected fiscal year, Company Code, and Assets highlighted by ZACORR110_B. After the values are updated, the repaired values in table ANLC appear like the ones shown in Figure 7 (these values are in line with line items in table ANEP).


Figure 7
Repaired values in table ANLC. Table ANLC is now reconciled with table ANEP

For the current fiscal year, also execute the depreciation recalculation program using transaction AFAR to recalculate the depreciation values.

Optimizing the Run Time for Material Ledger Activation in SAP S/4HANA

Starting from SAP S/4HANA 1511, activation of the Material Ledger for the purpose of inventory valuation is obligatory. Note that use of actual costing and transfer pricing is optional.

The activation process of the Material Ledger is very time-consuming with run times extending more than 20 hours. With a few precautions, you can optimize the run time to finish this activity in a reasonable amount of time.

Execute program R_FML_MIGRATION with a smaller package size. The smaller the package size, the better the chances of finishing the job in a reasonable time frame.

A package size of 500 or smaller helps to reduce the run time.

Use transaction code SE38 to access the program R_FML_MIGRATION. You would see the initial screen as in Figure 8.


Figure 8
The initial screen of program R_FML_MIGRATION

Use of parallel processing: Relevant Basis settings must be in place so that processes are executed in parallel.

Look out for any of the latest SAP Notes that fix the performance of the Material Ledger migration program. At the time of writing this article, the latest note is SAP Note 2344274.

An email has been sent to:





 

Ajay Maheshwari

Ajay Maheshwari (ajaycwa1981@gmail.com) is an SAP Finance and Controlling (FI/CO) and SAP S4/HANA solution architect with more than 13 years of experience. He is well known for his contributions to the SAP Community Network (SCN) Forum. He is among the all-time top 20 contributors to the SCN Forum, across all SAP modules and one of the top contributors in his own space, SAP FI/CO. He is one of the official SAP mentors and has been recognized as the topic leader in the SCN Forum each year since 2011. He has experience with SAP implementations and rollouts in several industries and thoroughly enjoys designing complex business processes and delivering SAP training in the areas of FI/CO and SAP S/4HANA. Currently, he works as associate director at itelligence, an SAP Platinum Partner.